Stay informed about construction works.
Welcome to our Construction Notifications page, where we keep the community informed about important construction updates and activities related to our project.
We are committed to transparency and ensuring that local residents, businesses, and stakeholders stay up to date with relevant information.
Check back regularly for updates.
2024
Multiple blasts scheduled in 2024 when conditions permit. Following is a schedule of controlled blasts planned at Tantangara worksite.
Tuesday 30 April between 5pm and 8pm - Tantangara Intake Structure - 90m exclusion zone
Tuesday 30 April between 4pm and 6pm - Tantangara Gate Shaft - 90m exclusion zone
Thursday 2 May between 7am and 9am - Tantangara Gate Shaft - 90m exclusion zone
Saturday 4 May between 5pm and 8pm - Tantangara Intake Structure - 90m exclusion zone
Monday 6 May between 5pm and 7pm - Tantangara Gate Shaft - 90m exclusion zone
Wednesday 8 May between 5pm and 8pm - Tantangara Intake Structure - 90m exclusion zone
Friday 10 May between 7am and 9am - Tantangara Gate Shaft - 90m exclusion zone
Sunday 12 May between 5pm and 8pm - Tantangara Intake Structure - 90m exclusion zone
Tuesday 14 May between 5pm and 7pm - Tantangara Gate Shaft - 90m exclusion zone
Thursday 16 May between 5pm and 8pm - Tantangara Intake Structure - 90m exclusion zone
Saturday 18 May between 7am and 9am - Tantangara Gate Shaft - 90m exclusion zone
Monday 20 May between 5pm and 8pm - Tantangara Intake Structure - 90m exclusion zone
Note the schedule is subject to change at short notice, particularly in relation to weather (especially rain and lightning) and the availability of specialist technical personnel.